QINGLV Construction and Demolition Waste This section describes the common faults and solutions of the treatment equipment

Blog
QINGLV Construction and Demolition Waste This section describes the common faults and solutions of the treatment equipment
Home > News > Blog > QINGLV Construction and Demolition Waste This section describes the common faults and solutions of the treatment equipment
Time:2025-01-15
Source:

QINGLV Construction and Demolition Waste recycling solutions are developed by Sanmei in response to the national energy conservation and environmental protection policy for Qinglv construction and demolition waste recycling. According to the characteristics of QINGLV Construction and Demolition Waste, the production line is designed through reasonable equipment configuration. At present, it has been put into actual production in many countries and regions at home and abroad, and has been praised by many customers.

QINGLV Construction and Demolition Waste Treatment equipment Introduction:

QINGLV Construction and Demolition Waste processing equipment is convenient and fast to realize the crushing, screening and impurity removal of QINGLV Construction and Demolition Waste. QINGLV Construction and Demolition Waste are removed by special iron removal equipment, coarse crushing, medium crushing and even fine crushing equipment, processed into a certain granularity of reclaimed sand and stone aggregate, and finally applied to roadbed stone, free brick, cement admixture, etc.

QINGLV Construction and Demolition Waste Application:

Crushing and screening of concrete fragments, asphalt blocks, bricks, stones, wood, plastic, gypsum and mortar, steel and non-metal etc.

Input material: QINGLV Construction and Demolition Waste mixture composed of road concrete blocks, asphalt concrete blocks, old building blocks, QINGLV Construction and Demolition Waste, etc.

Output products: iron, steel, impurities, plastics and stones and bricks of different sizes. All screening materials are ultimately used in road blocks, free bricks, cement admixtures, etc.

In the operation process of QINGLV Construction and Demolition Waste treatment equipment, there are always some faults, and it is troublesome to deal with them. The following is a look at the common troubleshooting equipment and solutions.

After the abnormal sound of the equipment itself, the flywheel continues to turn, but the E plate does not understand, and the spring of the tie rod is relaxed. The repair method is to open the nut of the tie rod screw, remove the spring of the tie rod, and then lift the jaw plate and replace the new thrust plate.

Two, QINGLV Construction and Demolition Waste treatment equipment inside the banging sound and the board shakes badly. The repair method is to shut down immediately, fix the crushing plate screw in the processing equipment, check whether the spring is not elastic enough, and if so, the spring needs to be replaced.

Third, the flywheel itself is not allowed to rotate, which may be that the crushing work is not carried out, and the thrust plate escapes the control of the support. Repair method, check the damage degree of the wearing parts, and replace the damaged parts.

Fourth, there are other abnormal sounds or abnormal banging sounds between the support and the broken plate. The repair method needs to check and re-adjust the device position of the discharge port, check the state of the spring, and decide whether to tighten the spring or replace the spring.

Fifth, the particle size of the finished product is too large. Repair method, it is necessary to adjust the adjustment device of the discharge port, reduce the discharge port, if not, you can replace the crushing board up or down or replace the new crushing board.

6. The crushing chamber is blocked, and the current of the main motor is higher than that of normal operation. Repair method: After stopping, use steel wire rope to tie the large stone and hoist the large stone out of the treatment equipment. Stop feeding, eliminate the fault of the belt conveyor, and try not to stop the processing equipment at this time. When stopping feeding, the discharge port should be dredged to slow down the speed of the feeder and reduce the feeding amount.

7, the bearing heat seriously exceeds the allowable temperature. Repair method, dredge, clean the oil pipe. Repair the oil pump. Clean the bearing shell and replace with new lubricating oil. Open the bearing, re-scrape the tile to increase the tile pad, adjust the clearance. Replace the appropriate lubricating oil. Remove cooling faults and pass lubricating oil through the cooler. Troubleshoot the bearing fantasy cooling water device.

Eight, the bearing oil leakage phenomenon, basically occurs in the bearing structure, the oil is from the middle through the bearing rocker, from both sides of the penetration. Repair method, replace the bearing shell, adjust the gap, so that the gap at both ends is greater than the gap in the middle.